HCC completes first tunnel for Mumbai Metro III project
With an average drilling rate of around 8.2 m per day, the 3.82-km long tunnel from CSMT to Mumbai Central via the station boxes at Kalbadevi, Girgaon and Grant Road, was completed surmounting various challenges, according to the company.
HCC team faced several geological and urban condition challenges, including the project?s proximity to the sea, tunnelling through heterogeneous reclaimed land, congested working areas and tunnelling below some of the oldest residential buildings that are over 100 years old. Overcoming all these challenges, the experienced HCC team managed to complete the tunnelling well within the stipulated timeline.
The Mumbai Metro Rail Corporation (MMRCL) had awarded the contract to HCC in July 2016, for the design and construction of twin tunnels by tunnel boring machine (TBM) method and construction of four underground metro stations at CSMT, Kalbadevi, Girgaum and Grant Road.
The construction of station buildings is currently underway. All the station buildings are unique in design. While the CSMT station is completely a cut and cover station, the remaining three stations would be made by NATM method.
Subscribe Now
Subscribe to our Newsletter & Stay updated
RECENT POSTS
Popular Tags
Folliow us
Related Stories
Hitachi to Supply Circuit-Breakers to Chubu Electric Power Grid
Hitachi announced that it received an order for five units of Hitachi Energy’s sulfur hexafluoride (SF6)-free EconiQ™ 300 kilovolt (kV) circuit...
Case CE Releases Limited-Edition 580 Super N Backhoe
Case CE has unveiled a special limited-edition model of its 580 Super N backhoe loader, with only 50 units available in the J.I. Case Signature E...
Cat Releases Small Dozer Simulator Training Programme
Novice operators can now get hands-on dozer training without climbing inside a cab with Simformotion’s new Cat Simulators Small Dozer system. U...