HCC completes first tunnel for Mumbai Metro III project
With an average drilling rate of around 8.2 m per day, the 3.82-km long tunnel from CSMT to Mumbai Central via the station boxes at Kalbadevi, Girgaon and Grant Road, was completed surmounting various challenges, according to the company.
HCC team faced several geological and urban condition challenges, including the project?s proximity to the sea, tunnelling through heterogeneous reclaimed land, congested working areas and tunnelling below some of the oldest residential buildings that are over 100 years old. Overcoming all these challenges, the experienced HCC team managed to complete the tunnelling well within the stipulated timeline.
The Mumbai Metro Rail Corporation (MMRCL) had awarded the contract to HCC in July 2016, for the design and construction of twin tunnels by tunnel boring machine (TBM) method and construction of four underground metro stations at CSMT, Kalbadevi, Girgaum and Grant Road.
The construction of station buildings is currently underway. All the station buildings are unique in design. While the CSMT station is completely a cut and cover station, the remaining three stations would be made by NATM method.

Subscribe Now
Subscribe to our Newsletter & Stay updated
RECENT POSTS
Popular Tags
Folliow us
Related Stories
JCB Hydromax Sets Hydrogen Land Speed Record at 406.320 mph
British engineering major JCB has set a new world land speed record with its hydrogen-powered JCB Hydromax, achieving an average speed of 406.320...
Schaeffler India Names Amit Bhalerao as Chief Operating Officer
Schaeffler India has appointed Amit Bhalerao as Chief Operating Officer (COO), effective August 10, 2026. He will lead the company's manufacturin...
BKT to Showcase Advanced Off-Highway Tyres at Bauma ConExpo
Balkrishna Industries Ltd (BKT) will showcase its latest off-highway tyre solutions at Bauma ConExpo India 2026, scheduled from September 15-18 a...