Mumbai Metro with 10 lines being built to serve Mumbai

Mumbai Metro with 10 lines is an urban Mass Rapid Transit System (MRTS) being built to serve Mumbai, Maharashtra?s capital and largest city.

Its development has been entrusted to the Mumbai Metropolitan Region Development Authority (MMRDA), who in 2004 came out with a 146.5 km master plan with multiple lines. Due to various issues which range from policy paralysis (EPC vs PPP, metro rail vs monorail) to environmental issues, the MMRDA has so far only been able to develop 1 metro line in the suburbs connecting Versova ? Andheri East ? Ghatkopar.

In 2015, a new 118 km master plan was approved and the then incumbent government provided much needed impetus for the development of 2 lines: Dahisar East ? Andheri East (Red Line) and Dahisar East ? D.N. Nagar (Yellow Line) in addition to the Cuffe Parade ? BKC ? Aarey Colony (Aqua Line).

In June 2019, a new nodal agency called Maha Mumbai Metro Operations Corporation (MMMOCL) was established for operating and maintaining all Mumbai Metro services on lines owned by MMRDA. In September 2019, the MMRDA unveiled a new 337 km master plan for Maha Mumbai Metro?s network consisting of 10 lines (total of 17 sections).

The Delhi Metro Rail Corporation has lent its services as the interim General Consultant for the execution of most lines.

Key Figures

Operational: 11.4 km | Under Construction: 169.061 km | Approved: 21.289 km | Proposed: 136.4 km


Line

Terminals / Corridor

Length (Km)

Stations

Status

Line-1

Verova ? Andheri ? Ghatkopar

11.4

12

Operational

Line-2A

Dahisar (E) ? DN Nagar

18.60

17

Under Construction

Line-2B

DN Nagar ? Mandale

23.64

22

Under Construction

Line-3

Cuffe Parade ? BKC ? Seepz ? Aarey Colony

33.50

27

Under Construction

Line-4

Wadala ? Kasarawadavali

32.32

32

Under Construction

Line-4A

Kasarawadavali ? Gaimukh

(extn of Line-4)

2.88

2

Under Construction

Line-5

Thane ? Bhiwandi ? Kalyan

24.95

17

12.811 km Under Construction; Rest On-Hold

Line-6

Swami Samarth Nagar ? Vikhroli

15.18

13

Under Construction

Line-7

Dahisar (E) ? Andheri (E)

16.5

14

Under Construction

Line-7A

Andheri (E) ? CSI Airport

(extn of Line-7)<

Related Stories

Over 2,600 Karnataka Real Estate Projects Delayed, Rs 6 Bn Refunds Owed

More than 2,600 real estate projects across Karnataka have missed their scheduled completion deadlines, with many now facing indefinite delays. B...

Read More

Assam Approves Rs 3.9 Billion Road Project to Boost Hill District Connectivity

In a landmark decision to enhance connectivity and promote tourism in Assam’s hill districts, the state government has approved a major road in...

Read More

Delhi L-G Approves Tree Removal for Nand Nagri Flyover Project

Lieutenant Governor VK Saxena has approved the transplantation and felling of 27 trees, clearing the final hurdle for the long-awaited flyover proj...

Read More