445 infra projects hits cost overrun of Rs 4.4 lakh crore
2022-01-25
According to a report, 445 infrastructure projects with an investment of Rs 150 crore each have been hit by cost overruns of over Rs 4.4 lakh crore.
The Ministry of Statistics and Programme Implementation looks into the infrastructure projects of Rs 150 crore or more. Of 1,673 projects, 445 faced cost overruns, and 557 projects were delayed.
The Ministry said that the initial implementation cost of these projects was Rs 22,23,791.78 crore, and their anticipated cost is likely to be Rs 26,64,649.18 crore, with Rs 4,40,857.40 crore cost overruns.
As per the report, the expenditure incurred on these infrastructure projects is Rs 13,08,766.65 crore, which is 49.12% of the anticipated cost of the projects.
The number of delayed projects dropped to 420 if the delay is counted based on the latest schedule of completion.
As many as 838 projects have not been given the year of commissioning nor the tentative gestation period.
From the 557 delayed projects, 97 projects have an overall delay between 1-12 months, 127 projects have been delayed for 13-24 months, 217 projects for 25-60 months and 116 projects for 61 months or more. The average time overrun in these projects is 45.69 months.
Time overruns were due to the issue of land acquisition, delay in forest and environment clearances, lack of infrastructure support and linkages. Other reasons include project financing, delay in finalising detailed engineering, change in scope, delay in the tendering process, ordering and equipment supply, law and order problems and Covid-19 restrictions and state-wise lockdowns.
Image SourceAlso read: China to rollout infra projects to combat economic slowdown Also read: BRO develops Project Yojak in Himachal Pradesh to boost road infra

Subscribe Now
Subscribe to our Newsletter & Stay updated
RECENT POSTS
Popular Tags
Folliow us
Related Stories
Ramky Infra Wins Rs 14.01 Billion Dighi Port Project
Ramky Infrastructure has secured an EPC contract worth Rs 14.01 billion from Maharashtra Industrial Township Limited (MITL) for infrastructure de...
Blum Launches CLIP top BLUMOTION 105° Hinge in India
Blum has introduced the CLIP top BLUMOTION 105° hinge in the Indian market, offering a universal solution designed to improve durability, function...
Runaya Ranks in Top 7% in S&P Global Sustainability Assessment
Runaya Metsource, a Vedanta company specialising in circular economy solutions and critical metal recovery, has ranked in the top 7 per cent glob...