Highway construction slows to 20.43 km/day in Apr-Jul period

While the pace had touched a record 37 km per day in 2020-21, it slowed to 28.64 km a day in 2021-22 due to COVID-19 pandemic-related disruptions and a longer-than-usual monsoon in some parts of the country.
"The ministry has constructed 2,493 km of National Highways up to July in 2022-23, as compared to 2,927 km constructed up to July 2021-22," the Ministry of Road Transport and Highways (MoRTH) said in its monthly summary for the Cabinet for July 2022.
According to the ministry data, only 1,975 km of road projects were awarded between April-July in 2022, compared to 2,434 km of road projects awarded in the year-ago period. The National Highways Authority of India (NHAI) and National Highways and Infrastructure Development Corporation Ltd (NHIDCL) are primarily responsible for the construction of national highways and expressways across the country.
The official target of highway construction has been kept at 12,000 km for the current financial year. The ministry had constructed 10,237 km in 2019-20, 13,327 km in 2020-21 and 10,457 km in 2021-22.
See also:
How new HAM criteria puts all on equal footing
NHAI to begin work on elevated highway in Chennai Port


Subscribe Now
Subscribe to our Newsletter & Stay updated
RECENT POSTS
Popular Tags
Folliow us
Related Stories
Hindustan Zinc Launches Inclusive Language Guide to Promote Workplace Diversity
Udaipur, 3rd July 2025: Hindustan Zinc Limited (NSE: HINDZINC), the world’s largest integrated zinc producer, has made a significant stride tow...
India Warehousing Show Concludes with Record Participation
The 14th edition of the India Warehousing Show (IWS) 2025 wrapped up successfully at Yashobhoomi (IICC), Dwarka, drawing over 300 exhibitors from...
BharatBenz Launches New Mining Range to Support India’s Infra Growth
Chennai, India: The Indian construction and mining equipment sector is set to grow significantly, projected to increase from $16 billion to $45 b...