BGRESL to commence work on Ennore thermal power station project

After five years, the physical work on the 660 MW Ennore thermal power station expansion project is likely to commence with the handing over of the site to the contractor BGR Energy Systems (BGRESL).

The ETPS expansion project site was handed over to the BGRESL in June and they have started work on the testing of the structures with a team of IIT Madras experts. After the completion of the tests, the contractor will commence the work.

ETPS expansion project work has been facing delay after delay. Tangedco awarded the EPC contract to Lanco Infra Tech (LITL) in May 2014. However, the LITL faced financial troubles and work came to a halt in August 2017. Tangedco terminated the contract in April 2018 ever since the project came to a standstill.

Related Stories

myHQ Report: Flexible Workspaces Dominate Demand

myHQ reports that 73 per cent of office space searches in India now favour flexible workspaces, with traditional leasing accounting for less than...

Read More

BITS Pilani Opens Smart Manufacturing Centre

BITS Pilani, through its Work Integrated Learning Programmes, inaugurated its Smart Manufacturing Competency Centre in Bengaluru, the second in a...

Read More

TK Elevator Begins India Factory Expansion Project

TK Elevator has commenced expansion of its manufacturing facility in India, marking a step towards strengthening local production and logistics c...

Read More

Reach out to us

Call Abin Antony
+91 8424 045 185 /
91-22-31033000

Schedule a Call Back