Mumbai Urja Marg commissions transmission lines in Gujarat

Sterlite Power’s arm Mumbai Urja Marg Transmission (MUML) has commissioned 400kV Banaskantha, Kansari and Vadavi transmission lines in Gujarat. The high-voltage transmission line will help in the evacuation of around 1,000 MW of renewable power from the pooling station at Bhuj in northern Gujarat to the national grid.

In addition to that, the transmission line, which has been commissioned four months ahead of schedule, will significantly augment the available power transmission capacity of the state, taking it from 9300 MW to 11200 MW.

Against India's renewable capacity of 90 GW, Gujarat's contribution stands at around 12 GW. On the back of its strong energy infrastructure, Gujarat aims to establish more than 67 GW of renewable energy by 2030.

Also read:
Sterlite Power rolls out Rs.16.62 bn transmission project in MP
Sterlite Power arm bags second lot in transmission auction in Brazil


Related Stories

myHQ Report: Flexible Workspaces Dominate Demand

myHQ reports that 73 per cent of office space searches in India now favour flexible workspaces, with traditional leasing accounting for less than...

Read More

BITS Pilani Opens Smart Manufacturing Centre

BITS Pilani, through its Work Integrated Learning Programmes, inaugurated its Smart Manufacturing Competency Centre in Bengaluru, the second in a...

Read More

TK Elevator Begins India Factory Expansion Project

TK Elevator has commenced expansion of its manufacturing facility in India, marking a step towards strengthening local production and logistics c...

Read More

Reach out to us

Call Abin Antony
+91 8424 045 185 /
91-22-31033000

Schedule a Call Back