Highway construction fails to achieve FY23 target

Gadkari stated that between April and November 2022-2023, around 2,038 km of 4/6/8 lane national highways were built, which is more than the 1,806 km built the previous year.
The length of two-lane national highways built this fiscal year was 1,607 kilometres, compared to 1,747 kilometres built the previous fiscal year.
The government is regularly reviewing sanctioned projects, and 719 delayed national highway projects have been found throughout several states as part of this operation, according to the ministry.
Out of the 2,431 ongoing projects in the country, approximately 719 are running behind schedule due to a protracted monsoon, above-average rainfall in some states, the Covid-19 pandemic, increases in raw material prices, particularly steel, issues with land acquisition, and statutory clearances, among other factors.
The minister also stated that no additional costs will be incurred as a result of the delayed projects.
See also:
Apr to Aug sees 19 km per day slowdown in highway construction
Highway building slows to 19.44 km per day in first half


Subscribe Now
Subscribe to our Newsletter & Stay updated
RECENT POSTS
Popular Tags
Folliow us
Related Stories
Mumbai’s Seaside Promenade Phase 1 Opens on 15 July
Mumbai, 7 July 2025 – The first phase of Mumbai’s long-awaited seaside promenade, part of the Coastal Road project, will open to the public o...
Rs 80 Million Road Inaugurated to Connect 20 Tribal Villages
A newly constructed 8-kilometre road connecting Pudi, Karangi, and Melikanchuru in Pachipenta mandal, Parvathipuram Manyam District, was inaugura...
Tata Steel to Launch Modular Bridges in India with InQuik
Tata Steel has signed a Memorandum of Understanding (MoU) with Australia-based InQuik Group to introduce modular bridge systems in India, aiming ...