MMRC completes 60% of Phase 1 track laying work on Mumbai Metro 3
According to the Mumbai Metro Rail Corporation (MMRC), which is constructing this line, track laying work on the underground Mumbai Metro Line 3 (Colaba-Bandra-SEEPZ) is currently close to 60% complete.Head Hardened (HH) rails, which can withstand approximately 50% more pressure than standard rails, were manufactured by a Japanese company and imported from Japan. For the first time in India, the Low Vibration Track (High Attenuation) technology is being used. These tracks will reduce the higher level of noise and vibration generated during train operations on this line, which is in the range of 22VdB (vibration measurement).
Recently MMRCL said that the first phase – Aarey to BKC – of the Colaba-Bandra-SEEPZ Metro-3 Corridor would be operationalised soon in 2023
According to MMRC, over 90% of the stations in Phase 1 are ready, and 55% of the system work is completed. The Metro 3 underground line has 26 stations in total, with nine underground stations in Phase 1. These stations are built at depths ranging from 20 to 29 metres.
See also:
Tailormade land acquisition strategy for Mumbai Metro 3
Mumbai Metro 3 project cost rises by Rs 10,269.82 crore

Subscribe Now
Subscribe to our Newsletter & Stay updated
RECENT POSTS
Popular Tags
Folliow us
Related Stories
Concord Control Systems bags ₹56.58 crore Indian Railways order for locomotive safety systems
Concord Control Systems has secured a ₹56.58 crore order from Indian Railways for the supply, installation and commissioning of locomotive wire...
Hafele expands Bengaluru footprint with new Appliances Studio in Bommasandra
Häfele India has expanded its retail footprint in Bengaluru with the launch of Appliances Studio Amro Interio, its third exclusive appliances stud...
Think Bold, Think Beautiful
A new material. A new technology. A new architectural typology. A new application. A deployment at scale.
In the rapidly evolving world of de...