60% of track laying work completed in Colaba-Bandra-SEEPZ Corridor

The first underground metro corridor in Mumbai is the 33.5-km-long Metro-3 corridor that runs along Colaba-Bandra-SEEPZ.
On August 30, Metro-3's Aqua Line's test run got under way.
Phase 1 of the project has accomplished 82% of its entire progress.
Phase 1 stations are almost 90% ready, and 55% of the system work has been completed.
In preparation for track laying work, the head hardened (HH) rails are being set up. The HH rails can sustain pressure that is over 50% more than normal rails can.
They are manufactured in Japan and imported there.
By installing these rails, the amount of 22VdB (vibration measurement) noise and vibration produced when the trains run will be reduced.
India will use the low vibration track (high attenuation) technology for the first time.
Also read:
L&T’s TBM Urja achieves third breakthrough of Bengaluru Pink Line
PM Modi to inaugurate Navi Mumbai Metro’s 5.96-km stretch


Subscribe Now
Subscribe to our Newsletter & Stay updated
RECENT POSTS
Popular Tags
Folliow us
Related Stories
Rajesh Power Services Bags Rs 9,219 Mn Orders from UGVCL
Rajesh Power Services Limited, a leading EPC contractor in power transmission and distribution, has announced new project wins worth Rs 9,219 mil...
Jindal Stainless to double slag processing with new USD 150 mn wet milling plant
In a major step toward circular manufacturing, Jindal Stainless, India’s largest stainless steel producer, is set to double its slag processing...