Biman Bandar metro completes building the diaphragm wall

This week marked a significant development in the metro project at the airport. On May 3, the diaphragm wall's construction was completed, giving the Biman Bandar metro station a boost.

The diaphragm wall, which connects the Jai Hind Metro Station to the Netaji Subhash Chandra Bose International Airport (NSCBI) terminal building, is in the subway, according to city metro authorities.

The cage on the wall is 17.405 meters long. It is around four meters wide and weighs about 15 metric tons. According to Kolkata Metro Railway, a traffic rerouting near the Airport Volvo bus stop was necessary to allow for the wall's construction.

The Airport Authority of India and the Bidhannagar Commissionerate had to approve it. Following approval, a traffic halt was implemented from 10.30 p.m. on May 30 to 7.56 a.m. on May 3.

The wall's construction was completed by the morning of May 3rd.

See also:
Construction of diaphragm wall for underground airport tunnel begins
Afcons kicks off a tunnel boring device without a diaphragm wall


Related Stories

Platinum Corp Launches Luxury Suites in Santacruz

Platinum Corp has recently launched Platinum Stellar: Bespoke Presidential Suites, a premium residential project in Santacruz West, Mumbai. The d...

Read More

Noida Airport Fuels NCR Realty Growth

The start of commercial operations at Noida International Airport has recently emerged as a major trigger for real estate growth across Noida, Gr...

Read More

RR Kabel features in Hurun India 500 list

RR Kabel has been featured in the 2025 Burgundy Private Hurun India 500, a list of India’s 500 most valuable companies. The list is compiled by...

Read More

Reach out to us

Call Abin Antony
+91 8424 045 185 /
91-22-31033000

Schedule a Call Back