Hyderabad Metro to have wide roads under Viaducts

According to the Hyderabad Metro Rail (HMRL), the MGBS-Falaknuma stretch of Corridor-II (Green Line) will feature 120-feet wide roads beneath the viaduct at all five stations. This decision was made in response to the challenges and congestion experienced during the implementation of phase-1, as stated by NVS Reddy, the managing director of HMRL. The construction process for this stretch will involve acquiring more than 1,000 properties.

it was anticipated that 103 religious structures, including 21 masjids, 12 temples, 12 ashoorkhanas, 33 dargahs, seven graveyards, and six chillas, would be affected. However, through engineering solutions such as adjusting the curvature and viaduct design, only four structures will ultimately be impacted. Officials claimed that MAUD minister KT Rama Rao had requested the preservation of these four structures by implementing engineering refinements, which are currently being addressed.

HMRL officials have initiated the process of creating individual sketches for the more than 1,000 properties expected to be affected. Land acquisition notices will be issued in approximately one month, according to NVS Reddy.

Related Stories

John Deere Unveils 5130M Tractor at Power & Technology Show

John Deere recently unveiled its new 5M series tractor, the 5130M (130 HP), during the company’s Power & Technology Show 7.0 in India. The ...

Read More

Blum India launches Blum Club app for carpenters and contractors

Blum India has introduced the Blum Club app, a dedicated loyalty platform designed for carpenters and contractors who install the company’s har...

Read More

India among fastest-growing real estate investment markets in APAC

Colliers has reported that India recorded one of the strongest growth rates in real estate investment across the Asia Pacific region in 2025, wit...

Read More

Reach out to us

Call us at +91 8108603000 or

Schedule a Call Back