GUVNL invites bids for battery energy storage systems

Gujarat Urja Vikas Nigam (GUVNL) has invited bids to set up pilot projects of 250 MW/500 MWh standalone battery energy storage systems (BESS) in Gujarat under tariff-based global competitive bidding (Phase-II).

The last day to submit the bids is January 6, 2023. Bids will be opened on January 10. Bidders must submit a bid processing fee of Rs 1.5 million ($17,993) and an earnest money deposit of Rs 740,000 ($8876)/ MW.

Selected bidders must furnish Rs 50,000 ($6,000)/ MW as a performance bank guarantee before signing the battery energy storage purchase agreement (BESPA).

The projects will be developed under a build, own, and operate model. GUVNL seeks to utilize energy storage systems on an on-demand basis, suited to the requirements of the state distribution companies during peak and off-peak hours.

The project must be completed within 18 months from the effective date of BESPA. The minimum bid size must be 140 MWh (70 MW x 2 hours)

Related Stories

NKN Media Taps Jacqueline Fernandez for International Property Expo

NKN Media has announced Jacqueline Fernandez as the celebrity face of its International Property Expo 2026, scheduled in New Delhi on 4–5 July....

Read More

Transvaal Training Returns as Judges at Forklift Competition

Transvaal Training has been confirmed as the official judging partner for the upcoming Forklift Driver Competition at Electra Mining Africa, foll...

Read More

Ammann India Launches CPB36 Truck Mounted Boom Pump

Ammann India has commercially launched the CPB36 truck-mountedom pump under the Ammann Elba brand, marking its entry into the concrete boom pump ...

Read More

Reach out to us

Call Abin Antony
+91 8424 045 185 /
91-22-31033000

Schedule a Call Back