Schedule a Call Back
NCLAT Clears Supertech to Resume Work on Doon Square in Dehradun
The approval paves the way for the project’s completion within 515 days, or just over one year and four months. Out of the 750 planned units, only 150 studio apartments have been delivered, with the remaining awaiting completion.
Supertech’s proposal, submitted to NCLAT, was accepted by the project's sole lender, Bank of Baroda, through a one-time settlement and repayment plan. Co-developer EBI Projects & Developments LLP has already deposited ?75 lakh as upfront payment, with ?42.5 million to be paid after NCLAT's approval and the remaining ?530 million in installments over 12 months.
The project has also received the consent of homebuyers, and an intervention application supporting Supertech’s request was filed. The interim resolution professional (IRP), Hitesh Goyal, confirmed there were no objections from stakeholders, clearing the way for construction to resume.
The tribunal’s decision, delivered on September 25, marks a key step toward the completion of the much-delayed Doon Square project.
Subscribe Now
Subscribe to our Newsletter & Stay updated
RECENT POSTS
Popular Tags
Folliow us
Related Stories
Bids Invited for 120 km Narmada River Cruise in Madhya Pradesh
The Madhya Pradesh Tourism Department has invited bids for operating a 120 km cruise expedition along the Narmada River, connecting Ekatma Dham (...
REC to Fund Health Equipment in Raipur, Chhattisgarh
REC Limited, a Maharatna CPSE under the Ministry of Power and a leading NBFC, has signed a Memorandum of Agreement (MoA) with the District Health...