45% Work Complete on Murkongselek–Pasighat Rail Line

Spanning 26.15 km, the project is being executed in two phases. In Phase I (Murkongselek to Sille – 15.60 km), earthwork is nearly complete, with 13.75 lakh cubic meters done out of a total 14.16 lakh cubic meters. Work on 18 major and 35 minor bridges is advancing steadily. Ballast supply and track linking are set to begin soon, and the Murkongselek station building is nearing completion.
Phase II (Sille to Pasighat – 10.55 km) has seen 3.55 lakh cubic meters of earthwork completed out of 6.85 lakh cubic meters. Bridge construction and casting are in progress, while land acquisition for a key road overbridge at Pasighat Yard is being expedited with local support.
Despite extended monsoon seasons and local disruptions, construction has continued at a steady pace. The NFR’s General Manager (Construction) recently inspected the site and emphasized timely completion while maintaining quality standards.
Once completed, the new railway line is expected to boost tourism, enhance national integration, and open up access to remote border areas of Arunachal Pradesh.
An NFR spokesperson reiterated Indian Railways’ commitment to executing this strategic infrastructure project, overcoming both environmental and logistical challenges.


Subscribe Now
Subscribe to our Newsletter & Stay updated
RECENT POSTS
Popular Tags
Folliow us
Related Stories
Maruti to Focus on SUVs but Won’t Abandon Small Cars
Maruti Suzuki India Ltd (MSIL), the country’s largest passenger vehicle manufacturer, reaffirmed its commitment to producing small cars while s...
Tamil Nadu Secures Rs 7 Billion Investment in Germany
Tamil Nadu has received investment commitments worth Rs 7.02 billion during Chief Minister M K Stalin’s visit to Germany, reinforcing the state...
Cities Key to India's 500 GW Green Energy Goal: WRI
Indian cities are increasingly emerging as key enablers of the country’s energy transition, serving as both major energy consumers and innovati...