CRS Inspects Final Stretch of Kolkata’s East-West Metro
2025-05-05

The final 2.6-kilometre stretch of Kolkata’s East-West Metro corridor, running through the challenging Bowbazar zone, underwent its crucial safety inspection by the Commission of Railway Safety (CRS) on Sunday, April 27. Once approved, this will complete the entire 16.6 km Green Line, marking a major milestone for the city’s metro network. “Once formal sanction is granted, passengers will be able to travel directly from Sector V to Howrah Maidan, crossing the Hooghly River,” said a Metro Railway spokesperson. The East-West Metro will then become fully operational, offering uninterrupted connectivity across the city for the first time.
Sumeet Singhal, Commissioner of Railway Safety (North Frontier Circle), led the inspection beginning at 9:00 AM. The assessment covered:
- Tunnel ventilation systems
- Track infrastructure
- Emergency evacuation procedures
- Passenger safety protocols
Singhal conducted speed trials at 80 kmph between Mahakaran and Central Park stations, and inspected systems at Esplanade station. He also reviewed sub-surface tunnel conditions on foot across both eastbound and westbound tracks—particularly through the subsidence-prone Bowbazar area, where unstable soil had previously caused severe delays.
The East-West Metro currently operates in two separate segments:
- Sector V to Sealdah – 9.2 km
- Esplanade to Howrah Maidan – 4.8 km
The missing link between Sealdah and Esplanade had faced prolonged construction challenges due to porous and unstable soil in Bowbazar, which led to ground subsidence and structural complications. Following the inspection, Metro officials confirmed that CRS expressed satisfaction with the project’s preparedness for passenger service.
Anuj Mittal, Managing Director of Kolkata Metro Rail Corporation (KMRC), along with senior Metro and Railway officials, accompanied the CRS team during the inspection. With final approval expected shortly, Kolkata is now on the cusp of launching its first fully connected East-West Metro corridor.


Subscribe Now
Subscribe to our Newsletter & Stay updated
RECENT POSTS
Popular Tags
Folliow us
Related Stories
Primegold Now Turns to Green Steel
Primegold International has rebranded itself as Primegold Steel & Power to reflect its entry into green steel production. The company is laun...
UP Targets Solar Growth with Global Ties
The Uttar Pradesh government is intensifying its policy-driven push for a green revolution by signing initial agreements with the Hinduja Group a...
Andhra to Get First E-Waste Facility at MedTech Zone
Andhra Pradesh MedTech Zone (AMTZ) in Visakhapatnam will host the state’s first integrated electronic waste management facility, setting a nati...