Toll Taken But Works Unfinished on Kerala’s 6-Lane NH Stretch

Vadakkencherry–Mannuthy, Kerala, 8 July 2025 – Toll collection on the 6-lane Vadakkencherry–Mannuthy National Highway (NH) began three years ago, yet over 30 construction works, including essential safety measures, remain incomplete (@mathrubhumi).

The toll began on 9 March 2022, under an agreement with Thrissur Expressway Ltd, which pledged to complete all pending works within 90 days. However, fewer than ten tasks have been finished to date (@mathrubhumi).

Despite this, the National Highways Authority of India (NHAI) issued a completion certificate on 14 June 2024, and imposed penalties on the concessionaire. Yet it is commuters who continue to face delays and pay tolls, particularly since rates at Panniyankara toll plaza exceed those at nearby plazas like Walayar and Paliyekkara (@mathrubhumi).

Major Pending Works
Key unfinished items include:
Landslide protection on steep slopes
Completion of a service road along the NH
Safety upgrades at junctions linking local roads
Construction of 21 bus bays and lorry parking at three sites
Installation of proper drainage and street lighting
NHAI officials confirmed that lorry bays are being planned, but offered no timeline on completing the remaining tasks (@mathrubhumi).

Impact on Road Users
Motorists have expressed frustration, as they continue to pay tolls for incomplete infrastructure, impacting safety and convenience. The disparity between toll fees and actual amenities has sparked concerns over accountability and transparency.

Related Stories

QNu Labs Validates ARMOS QKD in Global VIAVI Study

QNu Labs (www.qnulabs.com

), a global leader in end-to-end hybrid quantum cybersecurity solutions, has announced the findings of a rese...

Read More

Panasonic hosts Co.lab Studio IGNITION roadshow in Bengaluru

Panasonic Life Solutions India hosted the ‘Co.lab Studio by IGNITION Roadshow’ in Bengaluru, bringing together startups, ecosystem partners and...

Read More

Bondada Commissions 48.2 MWp Solar Projects

Bondada Engineering has commissioned 48.2 MWp of solar power projects in March 2026 for clients including Paradigm IT and MAHAGENCO across multip...

Read More

Reach out to us

Call Abin Antony
+91 8424 045 185 /
91-22-31033000

Schedule a Call Back