Schedule a Call Back
The Critical Path
2026-03-26
In Ircon International Ltd v. Afcons Infrastructure Ltd, OMP (Comm) 279/2019, the Delhi High Court examined how delay and extension of time (‘EOT’) are to be assessed in construction contracts, particularly in the context of the ‘critical path’ while dealing with challenge to an arbitral award under Section 34 of the Arbitration and Conciliation Act 1996 (‘the Act’). The High Court’s observations regarding the critical path are of significant import for construction and infrastructure projects and related arbitration.
The parties entered into a contract for construction of Tunnel T-74R on the Udhampur-Srinagar-Baramulla railway line. The project was to be completed within 33 months from the date of commencement, with 17 ‘key dates’ (KDs) prescribed under Appendix XV of the contract...
To read the full article Click Here

Subscribe Now
Subscribe to our Newsletter & Stay updated
RECENT POSTS
Popular Tags
Folliow us
Related Stories
144 Years in the Making!
1. A century-spanning construction story
Construction began in 1882, making the Sagrada Famí...
Read More
Almost all leading developers in India are using our
From digitising procurement to AI-led project monitoring, Bandhoo is transforming construction execution through its integrated SaaS ecosystem. I...
Scaling the Skies!
India’s aviation sector is entering a decisive phase – one where ambition is no longer defined by the number of airports being announced but by...
