Bullet Train Project Installs Five Portal Beams Over Ahmedabad
The Mumbai-Ahmedabad bullet train project has completed the installation of five heavy portal beams over active Indian Railways tracks at Maninagar in Ahmedabad within 22 days, marking a key engineering milestone. The precast prestressed portal beams were launched over the Ahmedabad-Vadodara railway line in a phased manner on April eight, 13, 19, 24 and 29, 2026, in close coordination with Indian Railways.
The operation involved the installation of beams weighing between 1170 metric tonnes (t) and 1360 t, the heaviest being lifted on April eight and counted among the heaviest lifts carried out on operational railway tracks in the country. Work was carried out over the Ahmedabad-Vadodara 'Up', 'Down' and third lines and required meticulous planning and coordination with rail traffic control.
The alignment at Maninagar passes above existing railway tracks at a raised level with limited space and spans of approximately 30 to 34 metres between piers, necessitating the use of heavy portal beam structures. These portal beams are designed to provide a strong and rigid support to transfer loads across multiple tracks, ensuring minimal deflection and preserving precise track alignment for safe railway operations.
The launching was carried out using a 2200 t crawler crane, its first deployment on Indian railway tracks, and each beam was installed in approximately three point five hours, significantly reducing the time compared with earlier operations that required up to nine-hour blocks. Despite constraints such as restricted working space, overhead electrification and ongoing train movement, the installation was completed with continuous monitoring and safety checks and adherence to safety protocols.
Each portal beam is a precast concrete structure measuring 34 metres long with a cross section of five point five metres by four point five metres and is installed as an integrated unit to support elevated infrastructure over railway lines. The use of precast prestressed elements allowed controlled factory conditions to ensure quality and consistency while reducing time at site and exposure to operational risks. Project authorities said the successful sequence of lifts will inform similar operations on future sections of the corridor.

Subscribe Now
Subscribe to our Newsletter & Stay updated
RECENT POSTS
Popular Tags
Folliow us
Related Stories
BG Pools Promotes Summer-Ready Outdoor Living in UAE
BG Pools + Landscape is promoting year-round outdoor living in the UAE through advanced pool technology, climate-adaptive landscaping and shaded ar...
ASK CLAF I invests in Goa luxury villa project
ASK Curated Luxury Asset Fund I, co-sponsored by India Sotheby’s International Realty and ASK Property Fund, has made its first investment in Goa...
Mekr Raises Rs 67 Crore Series A Funding Led by Avaana Capital
Mekr Technologies, a full-stack consumer electronics and appliance design and manufacturing platform, has raised Rs 67 crore in a Series A fundin...