Covid Corollaries: On the highway, four states of discomfort

Photo: For representational purpose

Construction of national highways came to a grinding halt with the nationwide lockdown imposed on March 25, 2020, to fight the COVID-19 pandemic. However, to the relief of developers, the government allowed resumption of construction  from April 20, subject to clearances from district administrations.

But activity remains stalled due to severe shortage of labour and raw material, and difficulty in securing requisite clearances.

What?s more, the Centre has divided districts into red, orange and green zones based on the extent of contagion. Only insitu construction is allowed in red zones until the next announcement.

As per a press note by CRISIL Research, the firm?s analysis of over 270 under-construction national highways indicates the top 10 states account for 80 per cent of the projects.

The zones of maximum risk

Projects are most at risk in four of these states ? Maharashtra, Uttar Pradesh, Tamil Nadu and Andhra Pradesh ? that account for over a third of the projects.

In Maharashtra, which has 11 per cent of the national highway projects, as much as 55 per cent of it is in red zones.

In Uttar Pradesh, which has the lion?s share of projects under construction at 15 per cent, a third is in the red zones.

Projects in Tamil Nadu and Andhra Pradesh, each with over 35 per cent projects in red zones, are also at risk.

In the milieu, for developers, containment of the pandemic and lifting of the extended lockdown are the key monitorables for a return to normalcy.

About a fifth of under-construction NHAI projects are in the red zones of the top 10 states

Those in Maharashtra, Uttar Pradesh, Gujarat, Tamil Nadu and Andhra Pradesh are at higher risk

Tags :

Related Stories

Durakraft uPVC Profiles Receive BIS Certification

Durakraft Extrusions has received the Bureau of Indian Standards (BIS) certification for its uPVC profiles used in windows and doors, reinforcing...

Read More

India Office Leasing Hits 43 Million Sq Ft in H1 2026: Cushman & Wakefield

India's office market recorded its strongest first-half leasing performance on record, with gross leasing volume (GLV) reaching approximately 43 ...

Read More

Peninsula Land Launches Villa Plot Project in Alibaug

Peninsula Land has launched Peninsula Estates, Alibaug ONE, an 11-acre plotted development offering 92 villa-ready plots in Alibaug, targeting ho...

Read More

Reach out to us

Call Abin Antony
+91 8424 045 185 /
91-22-31033000

Schedule a Call Back