Sikkim rail project reaches milestone with emergency exit tunnel completion

The Sivok-Rangpo Rail Project (SRRP), which will connect Sikkim to the railway network for the first time, has got a major boost with completion of an 855-metre-long emergency exit tunnel.
A 20-metre section of the tunnel runs below the National Highway-10 along the Teesta river and mining through its soft and loose soil, just like the river sand bed, was the most challenging part of the whole project as there was a high risk that it might cave in, snapping Sikkim's road connectivity with the rest of the country.
But the Railways succeeded in mining a tunnel in sandy soil below NH-10, while averting a cave-in risk and without causing a single millimetre of deformation to the highway. NH-10 is the only road network that connects Sikkim with other parts of the country.
The project, covering a 44.96 km between Sivok in West Bengal and Ranpo in Sikkim) has 14 tunnels, 22 bridges (13 major, nine minor) and five railway stations.
Indian Railway has set a new deadline of August 2025 to finish the SRRP that will connect Sikkim with the rest of the country through the rail network for the first time.


Subscribe Now
Subscribe to our Newsletter & Stay updated
RECENT POSTS
Popular Tags
Folliow us
Related Stories
Liebherr bets big on India’s kitchen market
Liebherr Appliances India, the subsidiary of the globally renowned €14.6 billion Liebherr Group known for its innovation & precision engineer...
DPRs Under Way For Metro Link From Bengaluru To Tumakuru
Karnataka Deputy Chief Minister D K Shivakumar has confirmed that detailed project reports are being drafted to extend both Namma Metro and inter-c...
Adani Commissions India’s First 5 MW Off-Grid Green Hydrogen Plant
Adani New Industries (ANIL) has announced the commissioning of India’s first off-grid 5 MW Green Hydrogen Pilot Plant at Kutch, Gujarat, marking ...